SSC CGL level Question Set 32, Work-time, Work-wages & Pipes-cisterns

32nd SSC CGL level Question Set, 1st exclusively on topics Work-time, Work-wages & Pipes-cisterns

SSC CGL Question Set 32 Work-Time Work-Wages Pipes-Cisterns

This is the 32nd question set of 10 practice problem exercise for SSC CGL exam and 1st exclusively on topics Work-time, Work-wages & Pipes-cisterns that are related. Students must complete this question set in prescribed time first and then only refer to the corresponding solution set for gaining maximum benefits from this resource.

In MCQ test, you need to deduce the answer in shortest possible time and select the right choice.

Based on our analysis and experience we have seen that, for accurate and quick answering, the student

  • must have complete understanding of the basic concepts in the topic area
  • is adequately fast in mental math calculation
  • should try to solve each problem using the basic and rich concepts in the specific topic area and
  • does most of the deductive reasoning and calculation in his or her head rather than on paper.

Actual problem solving is done in the fourth layer. You need to use your problem solving abilities to gain an edge in competition.

32nd question set- 10 problems for SSC CGL exam: 1st on topics Work-time, Work-wages & Pipes-cisterns - time 12 mins

Problem 1.

A team of 16 persons who can finish a job in 10 days start on the job together but after doing 80% of the job, 50% of the persons left the team. The number of additional days that will be required to complete the job will then be,

  1. 4
  2. 12
  3. 2
  4. 3

Problem 2.

If 6 weavers can weave 14 sarees in 14 days how many more weavers will be required for weaving 28 sarees in 7 days?

  1. 20
  2. 18
  3. 16
  4. 12

Problem 3.

Runu can do a piece of work in 12 days and Biju in 16 days. They begin together and with help of another man finish the work in 6 days. If they get a total wage of Rs.3200 for the work, how much Runu should get as his share of wage?

  1. Rs.1600
  2. Rs.1200
  3. Rs.800
  4. Rs.900

Problem 4.

Out of 120 poles to be erected 40 labourers could erect 40 poles in 4 hours. But after that 8 labourers fell ill and left the job. How many hours more will be required to finish erecting all the poles?

  1. 4
  2. 6
  3. 10
  4. 8

Problem 5.

7 men and 7 women can do a work in 2 days. How much time (in days) will 1 man and 1 woman take to do the same work?

  1. 7
  2. 1
  3. 14
  4. 49

Problem 6.

A piece of work can be done by $B$ in 12 days and by $A$ in 20 days. $A$ first worked on the job for a few days after which $B$ started the work replacing him. If the work was finally completed in total number of 14 days, after how many days from start did $A$ leave?

  1. 6
  2. 4
  3. 8
  4. 5

Problem 7.

$A$, $B$ and $C$ can do a piece of work in 20, 30 and 12 days respectively. $A$ and $B$ begin to do the work together and taking help of $C$ every third day complete the job. If they receive Rs.6000 as wages for the work, how much did $C$ receive (in Rs.)?

  1. 1800
  2. 1200
  3. 1500
  4. 1600

Problem 8.

A cistern can be filled up by two pipes $A$ and $B$ in 30 minutes and 20 minutes respectively. Both the pipes were opened together when the cistern was empty, but after a little while $B$ was stopped and the cistern got filled up in a total duration of 18 minutes. When was the pipe $B$ stopped (in minutes afer start)?

  1. 6
  2. 8
  3. 10
  4. 4

Problem 9.

If 30 men work they take 6 more days than 40 men would have taken to complete a work. How many days would 60 men take to complete the work?

  1. 8
  2. 12
  3. 10
  4. 6

Problem 10.

Ravi is thrice as fast as Mintu and is able to finish a work in 60 days less than Mintu. How long would they take (in days) to complete the work together?

  1. $18$
  2. $22\frac{1}{2}$
  3. $24\frac{1}{6}$
  4. $20\frac{2}{3}$

Useful resources to refer to

7 steps for sure success in SSC CGL Tier 1 and Tier 2 competitive tests

How to solve Arithmetic problems on Work-time, Work-wages and Pipes-cisterns

Basic concepts on Arithmetic problems on Speed-time-distance Train-running Boat-rivers

How to solve a hard CAT level Time and Work problem in a few confident steps 3

How to solve a hard CAT level Time and Work problem in a few confident steps 2

How to solve a hard CAT level Time and Work problem in few confident steps 1

How to solve Work-time problems in simpler steps type 1

How to solve Work-time problem in simpler steps type 2

SSC CGL Tier II level Solution Set 10 on Time-work Work-wages Pipes-cisterns 1

SSC CGL Tier II level Question Set 10 on Time-work Work-wages Pipes-cisterns 1

SSC CGL level Solution Set 67 on Time-work Work-wages Pipes-cisterns 6

SSC CGL level Question Set 67 on Time-work Work-wages Pipes-cisterns 6

SSC CGL level Solution Set 66 on Time-Work Work-Wages Pipes-Cisterns 5

SSC CGL level Question Set 66 on Time-Work Work-Wages Pipes-Cisterns 5

SSC CGL level Solution Set 49 on Time and work in simpler steps 4

SSC CGL level Question Set 49 on Time and work in simpler steps 4

SSC CGL level Solution Set 48 on Time and work in simpler steps 3

SSC CGL level Question Set 48 on Time and work in simpler steps 3

SSC CGL level Solution Set 44 on Work-time Pipes-cisterns Speed-time-distance

SSC CGL level Question Set 44 on Work-time Pipes-cisterns Speed-time-distance

SSC CGL level Solution Set 32 on work-time, work-wage, pipes-cisterns

SSC CGL level Question Set 32 on work-time, work-wages, pipes-cisterns