SSC CGL Time and Work Problems with answers Set 32
10 Time and Work Problems in SSC CGL Questions Set 32 to solve in 12 minutes. Verify correctness from answers. Learn how to solve from solutions.
Contents are,
- 10 selected Time and work problems for SSC CGL. These can easily be used for bank POs and other competitive exams.
- Answers to the time and work problems set.
Varieties of time and work questions and pipes and cisterns questions have been selected in this 32nd question set of 10 practice problem exercise for SSC CGL exam, so that some you may solve quickly and a few others not so quickly.
After doing this exercise in a timed session, you should refer to its solution set for detailed concepts and ways to solve the problems in mind as far as possible.
Answers and link to the solutions are at the end.
10 Time and work problems for SSC CGL Set 32—time 12 mins
Problem 1.
A team of 16 persons who can finish a job in 10 days start on the job together but after doing 80% of the job, 50% of the persons left the team. The number of additional days that will be required to complete the job will then be,
- 4
- 12
- 2
- 3
Problem 2.
If 6 weavers can weave 14 sarees in 14 days how many more weavers will be required for weaving 28 sarees in 7 days?
- 20
- 18
- 16
- 12
Problem 3.
Runu can do a piece of work in 12 days and Biju in 16 days. They begin together and with help of another man finish the work in 6 days. If they get a total wage of Rs.3200 for the work, how much Runu should get as his share of wage?
- Rs.1600
- Rs.1200
- Rs.800
- Rs.900
Problem 4.
Out of 120 poles to be erected 40 labourers could erect 40 poles in 4 hours. But after that 8 labourers fell ill and left the job. How many hours more will be required to finish erecting all the poles?
- 4
- 6
- 10
- 8
Problem 5.
7 men and 7 women can do a work in 2 days. How much time (in days) will 1 man and 1 woman take to do the same work?
- 7
- 1
- 14
- 49
Problem 6.
A piece of work can be done by $B$ in 12 days and by $A$ in 20 days. $A$ first worked on the job for a few days after which $B$ started the work replacing him. If the work was finally completed in total number of 14 days, after how many days from start did $A$ leave?
- 6
- 4
- 8
- 5
Problem 7.
$A$, $B$ and $C$ can do a piece of work in 20, 30 and 12 days respectively. $A$ and $B$ begin to do the work together and taking help of $C$ every third day complete the job. If they receive Rs.6000 as wages for the work, how much did $C$ receive (in Rs.)?
- 1800
- 1200
- 1500
- 1600
Problem 8.
A cistern can be filled up by two pipes $A$ and $B$ in 30 minutes and 20 minutes respectively. Both the pipes were opened together when the cistern was empty, but after a little while $B$ was stopped and the cistern got filled up in a total duration of 18 minutes. When was the pipe $B$ stopped (in minutes after start)?
- 6
- 8
- 10
- 4
Problem 9.
If 30 men work they take 6 more days than 40 men would have taken to complete a work. How many days would 60 men take to complete the work?
- 8
- 12
- 10
- 6
Problem 10.
Ravi is thrice as fast as Mintu and is able to finish a work in 60 days less than Mintu. How long would they take (in days) to complete the work together?
- $18$
- $22\frac{1}{2}$
- $24\frac{1}{6}$
- $20\frac{2}{3}$
The detailed explanation of solution to the questions in text is available at, SSC CGL Solution Set 32 Time and work, Work and wages, Pipes and cisterns.
Answers to the questions are given below.
Answers to the time and work problems for SSC CGL set 32
Q1. Answer: Option c: 2.
Q2. Answer: Option b : 18.
Q3. Answer: Option a: Rs.1600.
Q4. Answer: Option c: 10.
Q5. Answer: Option c: 14.
Q6. Answer: Option d : 5.
Q7. Answer: Option c: 1500.
Q8. Answer: Option b: 8.
Q9. Answer: Option b: 12.
Q10. Answer: Option b: $22\frac{1}{2}$.
Useful resources to refer to
Guidelines, Tutorials and Quick methods to solve Work Time problems
7 steps for sure success in SSC CGL Tier 1 and Tier 2 competitive tests
How to solve Arithmetic problems on Work-time, Work-wages and Pipes-cisterns
Basic concepts on Arithmetic problems on Speed-time-distance Train-running Boat-rivers
How to solve a hard CAT level Time and Work problem in a few confident steps 3
How to solve a hard CAT level Time and Work problem in a few confident steps 2
How to solve a hard CAT level Time and Work problem in few confident steps 1
How to solve Work-time problems in simpler steps type 1
How to solve Work-time problem in simpler steps type 2
How to solve a GATE level long Work Time problem analytically in a few steps 1
How to solve difficult Work time problems in simpler steps, type 3
SSC CGL Tier II level Work Time, Work wages and Pipes cisterns Question and solution sets
SSC CGL Tier II level Solution set 26 on Time-work Work-wages 2
SSC CGL Tier II level Question set 26 on Time-work Work-wages 2
SSC CGL Tier II level Solution Set 10 on Time-work Work-wages Pipes-cisterns 1
SSC CGL Tier II level Question Set 10 on Time-work Work-wages Pipes-cisterns 1
SSC CGL level Work time, Work wages and Pipes cisterns Question and solution sets
SSC CGL level Solution Set 72 on Work time problems 7
SSC CGL level Question Set 72 on Work time problems 7
SSC CGL level Solution Set 67 on Time-work Work-wages Pipes-cisterns 6
SSC CGL level Question Set 67 on Time-work Work-wages Pipes-cisterns 6
SSC CGL level Solution Set 66 on Time-Work Work-Wages Pipes-Cisterns 5
SSC CGL level Question Set 66 on Time-Work Work-Wages Pipes-Cisterns 5
SSC CGL level Solution Set 49 on Time and work in simpler steps 4
SSC CGL level Question Set 49 on Time and work in simpler steps 4
SSC CGL level Solution Set 48 on Time and work in simpler steps 3
SSC CGL level Question Set 48 on Time and work in simpler steps 3
SSC CGL level Solution Set 44 on Work-time Pipes-cisterns Speed-time-distance
SSC CGL level Question Set 44 on Work-time Pipes-cisterns Speed-time-distance
SSC CGL level Solution Set 32 on work-time, work-wage, pipes-cisterns
SSC CGL level Question Set 32 on work-time, work-wages, pipes-cisterns
SSC CHSL level Solved question sets on Work time
SSC CHSL Solved question set 2 Work time 2
SSC CHSL Solved question set 1 Work time 1
Bank clerk level Solved question sets on Work time
Bank clerk level solved question set 2 work time 2
Bank clerk level solved question set 1 work time 1