You are here

SSC CHSL Solved question Set 2, Work time 2

SSC CHSL time and work questions solved set 2

2nd Set of 10 Solved SSC CHSL time and work questions

Practice on 10 SSC CHSL time and work test questions in set 2.

Questions are solved by time and work techniques: working together, man hour, work rate, work wage.

The second set of solved time and work questions contains,

  1. 10 carefully selected questions on Time and work for SSC CHSL to be answered in 15 minutes.
  2. Answers to the questions, and
  3. Quick solutions to the questions.

For best results,

  1. Take the test first with timer on. Stop at 15 minutes.
  2. Verify how far your answers are correct from the answers.
  3. Clear your doubts and learn how to solve the questions quick and easy from the detailed solution set.

For quick solution of the questions, time and work concepts along with concepts on ratio and proportion, product of ratios, unitary method are used.

SSC CHSL time and work questions, Practice Set 2: Answering time 15 mins

Q1. If the work done by $(x-1)$ men in $(x+1)$ days is to the work done by $(x+2)$ men in $(x-1)$ days are in the ratio $9:10$, then the value of $x$ is,

  1. 8
  2. 7
  3. 6
  4. 5

Q2. 3 men and 7 women can do a job in 5 days, while 4 men and 6 women do it in 4 days. The number of days required for a group of 10 women working together at the same rate as before to finish the job is,

  1. 30 days
  2. 40 days
  3. 36 days
  4. 20 days

Q3. If there is a reduction in the number of workers in a factory in the ratio of $15:11$ and an increment of wages in the ratio of $22:25$, the ratio by which the total wages of the workers would be decreased is,

  1. $3:7$
  2. $5:6$
  3. $6:5$
  4. $3:5$

Q4. Debu and Monu take a piece of work for Rs.28,800. One alone could do it in 36 days and the other in 48 days. With the assistance of an expert they finish it in 12 days. How much remuneration the expert should get?

  1. Rs.10,000
  2. Rs.12,000
  3. Rs.18,000
  4. Rs.16,000

Q5. It was planned to construct a road 5 km long in 100 days and 280 workers were employed for the job. But after 80 days it was found that only $3\displaystyle\frac{1}{2}$ Km of the road was completed. How many more men need to be employed now to complete the work in planned time?

  1. 200
  2. 80
  3. 100
  4. 480

Q6. P can complete $\displaystyle\frac{1}{4}$th of a work in 10 days. Q can complete 40% of the same work in 15 days. R completes $\displaystyle\frac{1}{3}$rd of the work in 13 days and S completes $\displaystyle\frac{1}{6}$th of the work in 7 days. Who will be able to complete the work earliest?

  1. S
  2. P
  3. Q
  4. R

Q7. A and B can do a piece of work in 72 days, B and C can do it in 120 days and A and C can do it in 90 days.. When A, B and C work together, how much work will be finished by them in 3 days?

  1. $\displaystyle\frac{1}{40}$
  2. $\displaystyle\frac{1}{10}$
  3. $\displaystyle\frac{1}{20}$
  4. $\displaystyle\frac{1}{30}$

Q8. 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work?

  1. 12 days
  2. 8 days
  3. 10 days
  4. 6 days

Q9. A can do as much work as B and C together can do. A and B can do a piece of work in 9 hours 36 mins and C can do it in 48 hours. The time that B will take to complete the work alone is,

  1. 18 hours
  2. 12 hours
  3. 30 hours
  4. 24 hours

Q10. A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in,

  1. $8$ days
  2. $5\displaystyle\frac{1}{3}$ days
  3. $10$ days
  4. $5$ days

Answers to the SSC CHSL Time and Work Questions Practice Set 2

Q1. Answer: Option a: 8.

Q2. Answer: Option d : 20 days.

Q3. Answer: Option c: $6:5$.

Q4. Answer: Option b: Rs.12,000.

Q5. Answer: Option a: 200.

Q6. Answer: Option c : Q.

Q7. Answer: Option c: $\displaystyle\frac{1}{20}$.

Q8. Answer: Option b: 8 days.

Q9. Answer: Option d: 24 hours.

Q10. Answer: Option b: $5\displaystyle\frac{1}{3}$ days.


Solutions to the SSC CHSL Time and Work Questions Practice Set 2: Answering time was 15 mins

Q1. If the work done by $(x-1)$ men in $(x+1)$ days is to the work done by $(x+2)$ men in $(x-1)$ days are in the ratio $9:10$, then the value of $x$ is,

  1. 8
  2. 7
  3. 6
  4. 5

Solution 1: Problem analysis and solution by using man days as measure of work amount

By the first condition, work done by $(x-1)$ men in $(x+1)$ days is,

$W_1=(x-1)(x+1)$ man days.

We have expressed the work amount in terms of man days.

Similarly in the second case, the work done,

$W_2=(x+2)(x-1)$ man days.

By the third condition,

The two amounts of work done are in the ratio $9:10$. So,

$\displaystyle\frac{W_1}{W_2}=\frac{(x-1)(x+1)}{(x+2)(x-1)}=\frac{9}{10}$,

Or, $\displaystyle\frac{x+1}{x+2}=\frac{9}{10}$.

Cross-multiplying and simplifying,

$x=8$.

Answer: Option a: 8.

Key concepts used: Work time concept -- Man days concept -- Ratio and proportion.

Q2. 3 men and 7 women can do a job in 5 days, while 4 men and 6 women do it in 4 days. The number of days required for a group of 10 women working together at the same rate as before to finish the job is,

  1. 30 days
  2. 40 days
  3. 36 days
  4. 20 days

Solution 2: Problem solving by Work rate technique

Here two cases of work completion with two different combinations of workers are given.

Assume work portion done by a man and a woman in a day as, $M$ and $W$ respectively. These are the corresponding work rates. This is Work rate technique.

In this technique, work variables are expressed as work rates and the fraction arithmetic is transferred to the RHS on total work amount making it much simpler.

Assume work amount as $W_A$.

By the first two conditions then,

$5(3M+7W)=W_A$,

Or, $15M+35W=W_A$, and,

$4(4M+6W)=W_A$,

Or, $16M+24W=W_A$.

$M$ to be eliminated to get the value of work rate of a woman in terms of work portion done in a day.

Multiply the first equation by 16, the second by 15 and subtract the second result from the first,

$W_A=W(16\times{35}-15\times{24})$

$=20W(28-18)$

$=200W$.

As 10 women work in the third case,

$W_A=20(10W)$.

10 women working together will take 20 days to complete the work.

Answer: Option d: 20 days.

Key concepts used: Work rate technique -- Work time concept -- Solution to a pair of linear algebraic equation.

After writing first two equations, rest of the calculations could be carried out in mind.

Q3. If there is a reduction in the number of workers in a factory in the ratio of $15:11$ and an increment of wages in the ratio of $22:25$, the ratio by which the total wages of the workers would be decreased is,

  1. $3:7$
  2. $5:6$
  3. $6:5$
  4. $3:5$

Solution 3: Problem analysis and solution by Ratio and proportion and Product of ratios concepts

$\text{Total wage }=\text{Number of workers}\times{\text{Wage per worker}}$.

So multiplying the two given ratios we will get the ratio of total wages before and after,

$\text{Ratio of total wage of workers}=\displaystyle\frac{15}{11}\times{\displaystyle\frac{22}{25}}$

$=\displaystyle\frac{6}{5}$.

Answer: Option c: $6:5$.

Key concepts used: Work wage concept -- Ratio proportion concept -- Product of ratios -- HCF reintroduction technique.

Mathematical explanation of multiplication of two ratios - what it means

Let total wages in the before and after situations be $TW_1$ and $TW_2$.

In the first case, the before and after ratio of number of workers is,

$\displaystyle\frac{15}{11}=\frac{15x}{11x}$, where $15x$ and $11x$ are the actual number of workers and $x$ is the canceled out HCF reintroduced.

Similarly in the second case, the before and after ratio of wage per worker is,

$\displaystyle\frac{22}{25}=\frac{22y}{25y}$, where $22y$ and $25y$ are the actual wage per worker and $y$ is the canceled out HCF reintroduced.

As total wage is the product of number of workers and wage per worker,

$TW_1=xy(15\times{22})$, and

$TW_2=xy(11\times{25})$.

Taking ratio of the two total wages we get,

$\displaystyle\frac{TW_1}{TW_2}=\frac{15}{11}\times{\frac{22}{25}}$

$=\displaystyle\frac{6}{5}$.

You don't have to deduce the answer this way. This explanation shows how a product of two ratios can result in a third ratio. In fact, with clear concepts, the problem can easily be solved in mind.

Q4. Debu and Monu take a piece of work for Rs.28,800. One alone could do it in 36 days and the other in 48 days. With the assistance of an expert they finish it in 12 days. How much remuneration the expert should get?

  1. Rs.10,000
  2. Rs.12,000
  3. Rs.18,000
  4. Rs.16,000

Solution 4: Problem solving by earning to work portion done proportionality

By earning to work portion done proportionality concept,

Total earning of a worker is directly proportional to the portion of work done by the worker.

The portion of work completed by Debu and Monu in 12 days of working together is,

$\displaystyle\frac{12}{36}+\displaystyle\frac{12}{48}=\displaystyle\frac{1}{3}+\displaystyle\frac{1}{4}=\displaystyle\frac{7}{12}$ portion of the work.

As total earning is directly proportional to the portion of total work done which is worth a total earning of Rs.28,800, in 12 days of working together Debu and Monu will earn,

$\displaystyle\frac{7}{12}$th of the total earning, and the expert will earn the rest as,

$\displaystyle\frac{5}{12}$th of total earning

$=\displaystyle\frac{5}{12}\times{\text{Rs.28,800}}$

$=\text{Rs.12,000}$.

Answer: Option b: Rs.12,000.

Key concepts used: Work wage concept -- Work rate concept -- Earning proportional to work portion done concept -- Working together concept.

Q5. It was planned to construct a road 5 km long in 100 days and 280 workers were employed for the job. But after 80 days it was found that only $3\displaystyle\frac{1}{2}$ km of the road was completed. How many more men need to be employed now to complete the work in planned time?

  1. 200
  2. 80
  3. 100
  4. 480

Solution 5: Problem analysis and solution by man days concept

We will use man days as work measure.

280 workers working for 80 days results in,

$280\times{80}\text{ man days}=3\displaystyle\frac{1}{2}=\displaystyle\frac{7}{2}$ km of road work

Simplifying we get the work equivalence of,

$80\times{80}\text{ man days}=1$ km of road work.

Leftover work is, $5-3\displaystyle\frac{1}{2}=\displaystyle\frac{3}{2}$ km of road work

If $x$ be the number of workers completing this leftover work in 20 days we have the man days equivalence as,

$20x\text{ man days}=\displaystyle\frac{3}{2}$km of road work,

$=\displaystyle\frac{3\times{80}\times{80}}{2}$ man days of work, substituting man days equivalent to 1 km of road work,

Or, $x=480$ men

Extra number of worker required would then be,

$480-280=200$.

Answer: Option a: 200.

Key concepts used: Man days as work measure concept.

Q6. P can complete $\displaystyle\frac{1}{4}$th of a work in 10 days. Q can complete 40% of the same work in 15 days. R completes $\displaystyle\frac{1}{3}$rd of the work in 13 days and S completes $\displaystyle\frac{1}{6}$th of the work in 7 days. Who will be able to complete the work earliest?

  1. S
  2. P
  3. Q
  4. R

Solution 6 - Problem analysis and solution by comparing number of days required to complete the work

P can complete $\displaystyle\frac{1}{4}$th of a work in 10 days,

So, P completes the whole work in 40 days.

Q can complete 40% or $\displaystyle\frac{2}{5}$th of the same work in 15 days,

So, Q completes the whole work in $\displaystyle\frac{75}{2}=37.5$ days.

R completes $\displaystyle\frac{1}{3}$rd of the work in 13 days,

So, R completes the whole work in 39 days.

S completes $\displaystyle\frac{1}{6}$th of the work in 7 days,

So, S completes the whole work in 42 days.

Out of the four then Q takes minimum time of 37.5 days to complete work.

Answer: Option c : Q.

Key concepts used: Working time concept -- Work completion time as product of inverse of work portion and time to do the portion -- unitary method.

Q7. A and B can do a piece of work in 72 days, B and C can do it in 120 days and A and C can do it in 90 days. When A, B and C work together, how much work will be finished by them in 3 days?

  1. $\displaystyle\frac{1}{40}$
  2. $\displaystyle\frac{1}{10}$
  3. $\displaystyle\frac{1}{20}$
  4. $\displaystyle\frac{1}{30}$

Solution 7 - Problem analysis and excution by Work rate technique and working together concepts

Assuming $A_w$, $B_w$ and $C_w$ as the work rate or work portion done in a day by A, B and C respectively, by the three given conditions, 

$A_w+B_w=\displaystyle\frac{1}{72}W$, assuming total work as $W$,

$B_w+C_w=\displaystyle\frac{1}{120}W$, and

$C_w+A_w=\displaystyle\frac{1}{90}W$.

Adding the three we get work portion done in a day when A, B and C work together as,

$A_w+B_w+C_w=\displaystyle\frac{1}{2}\left(\displaystyle\frac{1}{72}+ \displaystyle\frac{1}{120}+\displaystyle\frac{1}{90}\right)W$

$=\displaystyle\frac{1}{60}W$.

So A, B, and C working together, will complete $\displaystyle\frac{1}{60}$th of the work in 1 day and $\displaystyle\frac{1}{20}$ th of the work in 3 days.

Answer: Option c: $\displaystyle\frac{1}{20}$.

Key concepts used:  Work rate of each worker in terms of work portion done in a day -- Work rate technique -- Working together concept, work portion done by workers working together is sum of their work rates -- Summing up three equations gives us the work portion done by all three together in a day.

Q8. 40 men can complete a work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work?

  1. 12 days
  2. 8 days
  3. 10 days
  4. 6 days

Solution 8 - Problem analysis and execution by man days concept

40 men complete a work in 18 days, and so the work amount is,

$40\times{18}=720$ man days.

In first 8 days 40 men complete, 320 mandays of work leaving 400 mandays work yet to be done.

On 9th day 10 more men joining, the team strength becomes 50 men.

To complete the left-out work of 400 mandays, this team of 50 men will require then,

$\displaystyle\frac{400}{50}=8$ days.

Answer: Option b: 8 days.

Key concepts used: Man days as work measure concept -- left-out work concept.

Q9. A can do as much work as B and C together can do. A and B can do a piece of work in 9 hours 36 mins and C can do it in 48 hours. The time that B will take to complete the work alone is,

  1. 18 hours
  2. 12 hours
  3. 30 hours
  4. 24 hours

Solution 9 - Problem analysis and execution by Work rate as work portion done in a day and Working together concept by adding work rates

A and B working together can complete the work in 9 hours 36 minutes or $9\displaystyle\frac{3}{5}=\frac{48}{5}$ hours.

Adopting Work rate technique, we assume work rates $a$, $b$ and $c$ as portion of work done in a day by A, B and C respectively, and $W$ as the whole work amount.

So by the second condition of A and B together doing the whole work in $\displaystyle\frac{48}{5}$ hours, we get one day work equivalence as,

$a+b=W\div{\displaystyle\frac{48}{5}}=\displaystyle\frac{5W}{48}$, Assuming $W$ as the whole work amount.

C does the work in 48 hours. So,

$c=\displaystyle\frac{W}{48}$

Also given, $a=b+c$. Substituting in the first equation,

$a+b=2b+c=\displaystyle\frac{5W}{48}$,

Or, $2b+\displaystyle\frac{W}{48}=\displaystyle\frac{5W}{48}$,

Or, $2b=\displaystyle\frac{W}{12}$,

Or, $b=\displaystyle\frac{W}{24}$.

It means B will complete the work in 24 hours.

Answer: Option d: 24 hours.

Key concepts used: Work rate technique -- Working together concept -- Efficient simplification.

Q10. A and B can do a work in 18 and 24 days respectively. They worked together for 8 days and then A left. The remaining work was finished by B in,

  1. $8$ days
  2. $5\displaystyle\frac{1}{3}$ days
  3. $10$ days
  4. $5$ days

Solution 10 - Problem analysis and solution by work rate and working together concepts

In 8 days, A and B working together complete portion of total work,

$8\left(\displaystyle\frac{1}{18}+\displaystyle\frac{1}{24}\right)=\displaystyle\frac{7}{9}$

So the leftout work is $\displaystyle\frac{2}{9}$th of the whole wotk.

B does the whole work in 24 days, so he will do $\displaystyle\frac{2}{9}$th of the whole work in,

$24\times{\displaystyle\frac{2}{9}}=\displaystyle\frac{16}{3}=5\displaystyle\frac{1}{3}$ days.

Answer: Option b: $5\displaystyle\frac{1}{3}$ days.

Key concepts used: Work rate concept -- Working together concept.



Useful resources to refer to

Guidelines, Tutorials and Quick methods to solve Work Time problems

7 steps for sure success in SSC CGL Tier 1 and Tier 2 competitive tests

How to solve Arithmetic problems on Work-time, Work-wages and Pipes-cisterns

Basic concepts on Arithmetic problems on Speed-time-distance Train-running Boat-rivers

How to solve a hard CAT level Time and Work problem in a few confident steps 3

How to solve a hard CAT level Time and Work problem in a few confident steps 2

How to solve a hard CAT level Time and Work problem in few confident steps 1

How to solve Work-time problems in simpler steps type 1

How to solve Work-time problem in simpler steps type 2

How to solve a GATE level long Work Time problem analytically in a few steps 1

How to solve difficult Work time problems in simpler steps, type 3

SSC CGL Tier II level Work Time, Work wages and Pipes cisterns Question and solution sets

SSC CGL Tier II level Solution set 26 on Time-work Work-wages 2

SSC CGL Tier II level Question set 26 on Time-work Work-wages 2

SSC CGL Tier II level Solution Set 10 on Time-work Work-wages Pipes-cisterns 1

SSC CGL Tier II level Question Set 10 on Time-work Work-wages Pipes-cisterns 1

SSC CGL level Work time, Work wages and Pipes cisterns Question and solution sets

SSC CGL level Solution Set 72 on Work time problems 7

SSC CGL level Question Set 72 on Work time problems 7

SSC CGL level Solution Set 67 on Time-work Work-wages Pipes-cisterns 6

SSC CGL level Question Set 67 on Time-work Work-wages Pipes-cisterns 6

SSC CGL level Solution Set 66 on Time-Work Work-Wages Pipes-Cisterns 5

SSC CGL level Question Set 66 on Time-Work Work-Wages Pipes-Cisterns 5

SSC CGL level Solution Set 49 on Time and work in simpler steps 4

SSC CGL level Question Set 49 on Time and work in simpler steps 4

SSC CGL level Solution Set 48 on Time and work in simpler steps 3

SSC CGL level Question Set 48 on Time and work in simpler steps 3

SSC CGL level Solution Set 44 on Work-time Pipes-cisterns Speed-time-distance

SSC CGL level Question Set 44 on Work-time Pipes-cisterns Speed-time-distance

SSC CGL level Solution Set 32 on work-time, work-wage, pipes-cisterns

SSC CGL level Question Set 32 on work-time, work-wages, pipes-cisterns

Bank clerk level Solved question sets on Work time

Bank clerk level solved question set 2 work time 2

Bank clerk level solved question set 1 work time 1


SSC CHSL level Question and Solution sets

Work and Time, Pipes and Cisterns

SSC CHSL level Solved Question set 1 on Work time 1

SSC CHSL level Solved Question set 2 on Work time 2

Number System, HCF and LCM

SSC CHSL level Solved Question set 3 on Number system 1

SSC CHSL level Solved Question set 4 on Number system 2

SSC CHSL level Solved Question set 5 on HCF and LCM 1

SSC CHSL level Solved Question set 6 on HCF and LCM 2

Surds and Indices

SSC CHSL level Solved Question set 7 on Surds and Indices 1

SSC CHSL level Solved Question set 8 on Surds and Indices 2

SSC CHSL level Solved Question set 17 on Surds and indices 3

Mixture or Alligation

SSC CHSL level Solved Question set 9 on Mixture or Alligation 1

SSC CHSL level Solved Question set 10 on Mixture or Alligation 2

Algebra

SSC CHSL level Solved Question set 11 on Algebra 1

SSC CHSL level Solved Question set 12 on Algebra 2

SSC CHSL level Solved Question set 13 on Algebra 3

SSC CHSL level Solved Question set 14 on Algebra 4

5th set of Solved algebra questions for SSC CHSL 18

6th set of solved algebra questions for SSC CHSL 19

Trigonometry

SSC CHSL level Solved Question set 15 on Trigonometry 1

SSC CHSL level Solved Question set 16 on Trigonometry 2